 700/742 Grayson Street Demolition

Project construction website · City of Berkeley COA 42

Demolition of the vacant industrial buildings at 700/742 Grayson Street, Berkeley, CA 94710. Owner: 742 Grayson Owner LLC (REDCO Development). Contractor: Inner City Demolition.

Building permit B2026-01620 · Use Permit ZP2021-0161, as modified by ZP2026-0053 · Last updated Nov 16, 2026

Current status: Pre-construction.
No work is happening on site yet. The demolition permit is in final City review. Anticipated start is early December 2026, after the permit is issued. This page will be updated with confirmed dates before work begins, and weekly during construction.

Questions and complaints

Construction hotline / Project Liaison: David Scott, Inner City Demolition (construction manager and Site Safety Director)
(951) 427-9963 · david@innercitydemolition.net
Call during work hours for noise, dust, traffic or site concerns.

Owner contact: Jason Freise, REDCO Development, for 742 Grayson Owner LLC
(949) 351-7030 · jfreise@redcodevelopment.com
Every complaint is logged, answered, and reported weekly to the City project planner.

Work hours

Monday–Friday: 7:00 AM – 6:00 PM
Saturday: 9:00 AM – 4:00 PM (lower-noise work only)
Sunday & holidays: No work
Hours per Use Permit Condition 39. No extended hours are planned; any extension would require City approval and a separate two-week neighbor notice.

Construction schedule

Tentative, assuming a start the week of December 7, 2026. Dates will be confirmed here.

  1. Mobilization · Wk 1 · Dec 7–8 · Fencing, signage, stormwater controls, stabilized entrance, traffic control set-up

  2. Hazardous materials abatement · Wk 1–3 · Dec 9–23 · Asbestos, lead, PCB, mercury and universal waste removal

  3. Utilities and sewer cap · Wk 2–3 · Dec 14–23 · Final utility terminations; sewer lateral capped; Public Works inspection

  4. Soft strip and salvage · Wk 4 · Dec 28 – Jan 1 · Removal of non-structural materials and recyclables

  5. Structural demolition · Wk 5–9 · Jan 4 – Feb 5 · Building demolition west to east with dust control

  6. Slab, foundation and paving removal · Wk 10–14 · Feb 8 – Mar 12 · Concrete and asphalt removal and recycling

  7. Grading and demobilization · Wk 15–17 · Mar 15 – Apr 2 · Rough grading, final erosion control; site left fenced and secured

Phase supervisor for all phases: David Scott, (951) 427-9963. Dates may shift for weather, holidays and inspections; changes will be posted here and reported to the City Zoning Officer.

This week

Week of Nov 16: No site work. Permit review and pre-construction coordination only.
Truck routes, lane closures and parking changes follow the Transportation Construction Plan below.

Project documents

Final Conditions of Approval – ZP2026-0053 Notice of Decision with conditions

Mitigation Monitoring and Reporting Program – Not applicable. The project is categorically exempt from CEQA (Guidelines §15332), so no MMRP was adopted.

Transportation Construction Plan – truck routes, staging, lane and sidewalk closures (COA 48)

Construction Noise Reduction Program – Illingworth & Rodkin, Nov 2, 2026

Building Materials Survey (air quality) – B2 Environmental, Nov 2, 2026

Soil Management Plan – dust and soil handling procedures, 2022

Bay Area Air Quality Management District notification – J# T204447 (updated acknowledgement to be posted)

500-ft neighbor construction notice – mailed November 4, 2026 (COA 21)

742 Grayson Owner LLC · REDCO Development · City of Berkeley permit B2026-01620